A Suzhou Industrial Park government report dated 7 November 2024 records establishment of IHI-Sullair Compression Technology (Suzhou) in 2004.
Suzhou
IHI-Sullair: centrifugal air and engineered nitrogen duties
Choose the actual series duty, distinguish the manufacturing parties and plan utilities, controls and acceptance.

IHI寿力压缩技术(苏州)有限公司 · SUZHOU, JIANGSU
Centrifugal compressor systems, with distinct contracting and manufacturing parties
IHI-Sullair supplies centrifugal compressors, associated systems and service. Its official profile describes joint investment by Japanese IRM and US Sullair, with T-series standard machines and engineered f-series equipment for industrial air and process duties.
The official profile names 石川岛寿力回转科技制造(苏州)有限公司 in the Suzhou–Xiangcheng Cooperation Zone for large f-series equipment. The government report records inauguration on 5 November 2024.
The new production-base entity and the original company are distinct names. Confirm the order’s contracting, manufacturing, testing and service responsibilities. The Changyang Street company address is not automatically the new factory’s address.

TX · TRE/TRA · f
Read these as family envelopes, then obtain the exact duty sheet
| Selection | Pressure envelope | Power envelope | What to resolve |
|---|---|---|---|
| TX centrifugal air | 4–9 barg | 150–425 kW | Named model, delivered air duty and control curve. |
| TRE/TRA centrifugal air | 2–16 barg | 180–1250 kW | Offered duty, utilities and horizontally split service access. |
| f engineered air/nitrogen | 1.5–65 barg | 1000–20000 kW | Process gas and inlet envelope; project-specific engineered supply. |
These are series ranges, not every possible motor/pressure combination. Request flow at defined intake/reference conditions and the actual offered pressure. Do not assign a different series’ capacity or treat a portfolio chart as a guaranteed performance map.


Control and part-load operation
TX and TRE/TRA descriptions list inlet-guide-vane regulation and constant-pressure plus load/unload control. Request minimum stable flow, usable regulation, blow-off/bypass behavior, network sequencing and total package input at your demand profile.
Oil-free gas path, lubricated machinery
The manufacturer describes oil-free compression. Gearbox/bearing lubrication is a separate boundary; installation materials include lubricant filling. Specify outlet water, oil and particle limits and treatment instead of assuming an ISO8573 class or current certificate.
ENGINEERED f SYSTEM · AIR/NITROGEN COMPRESSION AND BOOSTING
Define the gas and inlet envelope before the machine

The f page describes customized air/nitrogen compression and boosting, guide-vane regulation and horizontally split service access. A nitrogen booster is not a nitrogen generator. It handles already available gas at specified inlet conditions.
- Gas and suction
- Composition/purity, contaminants or liquid risk, pressure and temperature extremes.
- Required duty
- Reference volume, normal/base/peak flow, receiving pressure and operating profile.
- Engineering boundaries
- Gas-path materials/seals, allowable carryover, cooling and drive supply, protections and process interlocks.
Obtain an offered performance map and stable operating limits. A wide pressure/power envelope does not establish one machine’s suitability for every gas or condition.
Prepare an engineered f duty →RECEIVING → FOUNDATION → ALIGNMENT → COMMISSIONING
Plan the installation and future removal access
The official installation library names receiving/storage/lifting, site and foundation checks, compressor placement, piping, electrical work, removal of preservation paper/grease, alignment and lubricating-oil filling. Use the delivered model’s instructions and trained personnel; these topics do not supply universal clearances or alignment tolerances.
Before shipment
Agree mass, lifting points, preservation/storage conditions, foundation loads and actual dimensions. Identify shipping splits and site receiving responsibility.
Before connection
Obtain pipe supports/nozzle loads, cooling utilities, voltage/phase/frequency, electrical protection and control/interlock schedules. Define installation and alignment responsibility.
During service
Reserve model-specific cover, rotor and auxiliary removal/lifting space. General maintenance wording allows internal inspection through the gearbox upper cover without removing unrelated air/water piping; the actual service procedure controls the work.
- Performance: offered capacity, total input, pressure, reference conditions and usable control range.
- Gas/air interface: purity/treatment, utilities, protection setpoints and receiving-process acceptance.
- Delivery support: factory/site tests, manuals, wear parts/spares, commissioning/training and warranty commencement/exclusions.
Questions for an IHI-Sullair proposal
Does 4–9 barg mean absolute pressure?
No. Barg is gauge pressure. Keep pressure conventions explicit in the model sheet, process interfaces and performance tests.
Can a TX airflow be copied into the f-series offer?
No. Series envelopes do not provide an interchangeable capacity. The offered model needs its own intake, flow reference, pressure and performance map.
Does oil-free mean no lubricating oil is used anywhere?
No. Gas-path wording differs from drive/bearing lubrication. The installation library includes oil filling; agree actual outlet-quality acceptance separately.
Send the air duty or process-gas envelope
Select TX, TRE/TRA or engineered f and include demand, inlet/delivery conditions, utilities and test requirements.
Prepare an IHI-Sullair RFQSpecification pages
Specification pages for IHI-Sullair product types
| Duty | Write on the RFQ |
|---|---|
| Compressor for wastewater treatment | Most aeration trains want low-pressure blowers. If this RFQ is actually 7–8 bar plant air for valves and instruments, say so — it is a different machine from a maglev blower. |
| Centrifugal compressor manufacturers in China | Centrifugal machines are duty-built. A 250 kW “centrifugal compressor China” RFQ without gas, suction and discharge pressure cannot be quoted. |
Product information
Information reviewed 2026-10-08. Specifications apply only to the models and conditions stated.
IHI-Sullair: Choose the actual series duty, distinguish the manufacturing parties and plan utilities, controls and acceptance.